Missouri certificate of need

Missouri has a certificate of need program, run by Missouri Health Facilities Review Committee, staffed by the Certificate of Need Program in the Missouri Department of Health and Senior Services. It covers 3 kinds of services, listed below.

Verified Oct 6, 2026Sources: official state and federal agencies

CON program
Yes
Services covered
3
On this page
Certificate of need

Missouri CON program

Missouri has a certificate of need program, run by Missouri Health Facilities Review Committee, staffed by the Certificate of Need Program in the Missouri Department of Health and Senior Services. It covers 3 kinds of services, listed below.

CON program
Yes
Program
Certificate of Need
Application fee
Greater of $1,000 or 0.1% of total project cost; filing starts when both application and fee are received (RSMo 197.315.10).
Review timeline
Committee notifies the applicant within 15 days whether the application is complete, holds a public hearing if an affected person asks within 30 days of the review notice, and issues its decision within 100 days of filing; it may extend by up to 30 days (RSMo 197.330).
Recent changes
State-operated facilities are deemed to hold a CON without a fee, except as specified for state-operated hospitals (RSMo 197.315.16).
Statute
RSMo §§197.300–197.367
Scope

Services that need a certificate of need

  • beds in long-term care facilities licensed under RSMo chapter 198 and hospital long-term care beds (expenditure minimum $600,000 capital / $400,000 major medical equipment)
  • long-term care hospitals (no expenditure minimum)
  • other health care facilities, new institutional health services and beds, including hospitals ($1,000,000 capital / $1,000,000 major medical equipment)
FAQ

Frequently asked questions

Does Missouri have a certificate of need law?

Missouri has a certificate of need program, run by Missouri Health Facilities Review Committee, staffed by the Certificate of Need Program in the Missouri Department of Health and Senior Services. It covers 3 kinds of services, listed below.

How long does a Missouri CON review take?

Committee notifies the applicant within 15 days whether the application is complete, holds a public hearing if an affected person asks within 30 days of the review notice, and issues its decision within 100 days of filing; it may extend by up to 30 days (RSMo 197.330).

How much is a Missouri CON application?

Greater of $1,000 or 0.1% of total project cost; filing starts when both application and fee are received (RSMo 197.315.10).